KHNP considers Hyundai and Samsung for Dukovany construction work
South Korea’s KHNP is considering Hyundai Engineering & Construction and Samsung C&T to carry out construction work on two new nuclear reactors at Dukovany, Czech Television reported on Saturday, citing KHNP executive vice-president Choi Il-kyung.
KHNP ended talks with its original Korean construction consortium in October without reaching an agreement and plans to launch a new tender. The company says it still intends to complete the project on schedule and at the agreed price, and aims to select a contractor by July next year.
The project is the largest investment in Czechia, with the two reactors expected to cost around CZK 407 billion. Construction of the first reactor is due to begin in 2029, with completion planned for 2036.