Areva appeals its exclusion from Temelin tender

France’s Areva has appealed against ČEZ’s decision to exclude it from a 10 billion dollar tender for the completion of the Temelin nuclear power plant in south Bohemia. The state-owned French company addressed all the reasons given for its exclusion and said its offer was the most competitive. ČEZ has 10 days to review Areva’s appeal and publish its decision. In the event of a rejection, Areva would be entitled to file a complaint to the Czech anti-monopoly office, which would have 60 days to review the case. Areva was rejected from the tender for allegedly failing to meet legislative and commercial requirements. Westinghouse Electric Corp. and a Russian-Czech group led by Rosatom Corp.’s unit ZAO Atomstroyexport are still competing for the deal to build two more nuclear reactors at Temelin. ČEZ should choose the winner in mid- 2013 and sign a final contract with the respective company by the year’s end.